Project Size: 2600 sf
Project Cost: $193,751
Construction Time: 60 days
Architect: The Samuel Group Description: Demolition of the existing
remote teller houses and the construction of a modern seven lane drive-thru
with a remote ATM enclosure. Demolition, curb and gutter, asphalt paving,
concrete, structural steel, wood trusses, architectural asphalt fiberglass
shingles, architectural exterior woodwork, drive-up teller line & teller
window, pneumatic tube system including a commercial box type kiosk (this
drive-thru was a reverse flow line and did not have a deal drawer). Special considerations: Construction was
completed while the banking center was in operation (the drive-thru was
closed) and the banking center was not adversely affected. The project was
completed on time. All of the drive-up teller stations opened on schedule.
Lead Architect: Mesfin Samuel
![]()
|
![]()
|
![]()
|
![]()
|
![]()
|